Sure, I'll provide detailed explanations for each term:
### (i) Average Demand
**Average Demand** refers to the average amount of electrical power or energy required over a specific period. It is calculated by dividing the total energy consumption over that period by the duration of the period. This term helps in understanding the typical load that needs to be met by the power system or the capacity required to meet the average consumption.
**Formula:**
\[ \text{Average Demand} = \frac{\text{Total Energy Consumption}}{\text{Total Time Period}} \]
**Example:**
If a factory consumes 10,000 kWh of electricity over a month (30 days), the average demand would be:
\[ \text{Average Demand} = \frac{10,000 \text{ kWh}}{30 \text{ days} \times 24 \text{ hours/day}} \approx 13.89 \text{ kW} \]
### (ii) Load Factor
**Load Factor** is a measure of the efficiency with which a system or plant operates. It compares the average demand to the peak demand over a specific period. A higher load factor indicates that the system is being used more consistently and efficiently.
**Formula:**
\[ \text{Load Factor} = \frac{\text{Average Demand}}{\text{Peak Demand}} \]
**Example:**
If a power plant has an average demand of 50 MW and a peak demand of 80 MW, the load factor would be:
\[ \text{Load Factor} = \frac{50 \text{ MW}}{80 \text{ MW}} = 0.625 \text{ or } 62.5\% \]
### (iii) Plant Capacity Factor
**Plant Capacity Factor** is a measure of the actual output of a power plant compared to its maximum possible output if it operated at full capacity all the time. It reflects how effectively a plant uses its installed capacity over a given period.
**Formula:**
\[ \text{Plant Capacity Factor} = \frac{\text{Actual Energy Output}}{\text{Maximum Possible Energy Output}} \]
Where:
- **Actual Energy Output** is the total energy produced by the plant.
- **Maximum Possible Energy Output** is the energy that would be produced if the plant operated at full capacity for the entire period.
**Example:**
If a plant with a maximum capacity of 100 MW operates for 4,000 hours in a year and produces 300,000 MWh of energy, its capacity factor would be:
\[ \text{Maximum Possible Output} = 100 \text{ MW} \times 4,000 \text{ hours} = 400,000 \text{ MWh} \]
\[ \text{Plant Capacity Factor} = \frac{300,000 \text{ MWh}}{400,000 \text{ MWh}} = 0.75 \text{ or } 75\% \]
### (iv) Plant Use Factor
**Plant Use Factor** (or **Utilization Factor**) measures the extent to which a power plant’s capacity is utilized in comparison to the installed capacity. It is similar to the plant capacity factor but often expressed in terms of the actual output compared to the installed capacity.
**Formula:**
\[ \text{Plant Use Factor} = \frac{\text{Actual Energy Output}}{\text{Installed Capacity} \times \text{Total Time Period}} \]
**Example:**
If the same plant with an installed capacity of 100 MW produces 300,000 MWh of energy over a year (8,760 hours), the use factor would be:
\[ \text{Plant Use Factor} = \frac{300,000 \text{ MWh}}{100 \text{ MW} \times 8,760 \text{ hours}} \approx 0.342 \text{ or } 34.2\% \]
In summary:
- **Average Demand** gives a sense of typical load.
- **Load Factor** indicates efficiency relative to peak demand.
- **Plant Capacity Factor** assesses the effectiveness of plant output relative to maximum potential.
- **Plant Use Factor** measures how much of the installed capacity is actually used.