🔍
A plant consists of two 10 MVA generators of reactance 18% each and two 5 MVA generators of 12% each. All are connected to bus bar to supply a load through three step up transformers of 8 MVA each having reactance of 8%. Determine fault MVA on HV side of any one transformer.

2 Answers

 
Best answer
To determine the fault MVA on the high voltage (HV) side of one transformer, we need to find the total equivalent reactance of the system and then use it to calculate the fault MVA. Here's a step-by-step method to solve this problem:

### 1. Convert All Reactances to a Common Base

First, we need to convert the reactances of all generators and transformers to a common base. Typically, this base is chosen to be the rating of one of the transformers or generators, but for simplicity, we will use the base of the transformers (8 MVA) here.

#### Generators

**Base Power for Conversion**: 8 MVA (Transformers' rating)

**Generator 1 Reactances**:
- **10 MVA generators** with **18% reactance** (0.18 per unit on 10 MVA)

  \[
  X_{gen1} = 0.18 \times \frac{10 \text{ MVA}}{8 \text{ MVA}} = 0.225 \text{ per unit on 8 MVA base}
  \]

**Generator 2 Reactances**:
- **5 MVA generators** with **12% reactance** (0.12 per unit on 5 MVA)

  \[
  X_{gen2} = 0.12 \times \frac{5 \text{ MVA}}{8 \text{ MVA}} = 0.075 \text{ per unit on 8 MVA base}
  \]

#### Transformers

**Transformers** are already on the 8 MVA base:
- **Reactance**: 8%

  \[
  X_{tr} = 0.08 \text{ per unit on 8 MVA base}
  \]

### 2. Find the Total Equivalent Reactance

**Reactance of Generators**:

We have:
- Two 10 MVA generators: \( X_{gen1} = 0.225 \text{ per unit} \)
- Two 5 MVA generators: \( X_{gen2} = 0.075 \text{ per unit} \)

**Calculate Total Equivalent Reactance of Generators**:

For generators with equal rating, we can calculate their combined reactance as:

\[
\frac{1}{X_{gen_{total}}} = \frac{1}{X_{gen1}} + \frac{1}{X_{gen2}}
\]

where:
- Two 10 MVA generators: \( X_{gen1} = 0.225 \text{ per unit} \)
- Two 5 MVA generators: \( X_{gen2} = 0.075 \text{ per unit} \)

Combined reactance of the generators:
- Two 10 MVA generators in parallel: \( X_{gen_{10MVA}} = \frac{0.225}{2} = 0.1125 \text{ per unit} \)
- Two 5 MVA generators in parallel: \( X_{gen_{5MVA}} = \frac{0.075}{2} = 0.0375 \text{ per unit} \)

Total combined reactance of all generators:
\[
\frac{1}{X_{gen_{total}}} = \frac{1}{0.1125} + \frac{1}{0.0375} = 8.8889 + 26.6667 = 35.5556
\]
\[
X_{gen_{total}} = \frac{1}{35.5556} = 0.0281 \text{ per unit}
\]

**Total System Reactance**:

The total reactance seen at the bus bar, including the transformers:
- Reactance of each transformer: 0.08 per unit
- Three transformers in parallel:

  \[
  X_{tr_{total}} = \frac{0.08}{3} = 0.0267 \text{ per unit}
  \]

  Combined reactance of all transformers:
  \[
  X_{total} = X_{gen_{total}} + X_{tr_{total}} = 0.0281 + 0.0267 = 0.0548 \text{ per unit}
  \]

### 3. Determine the Fault MVA

To determine the fault MVA, use the formula:
\[
\text{Fault MVA} = \frac{\text{Base MVA}}{X_{total}}
\]

Here, the base MVA is 8 MVA (transformer base):
\[
\text{Fault MVA} = \frac{8}{0.0548} = 145.8 \text{ MVA}
\]

So, the fault MVA on the HV side of one transformer is approximately **145.8 MVA**.
0 like 0 dislike
To determine the fault MVA on the HV side of one transformer, follow these steps:

1. **Convert Generator and Transformer Reactances to a Common Base:**
   - Base MVA: 8 MVA (since the transformers are 8 MVA)

2. **Convert the Generators' Reactances to the Transformer Base:**

   - For the 10 MVA generators (Reactance = 18%):
     \[
     X_{10 \text{ MVA}} = \frac{18}{100} \times \frac{8}{10} = 0.144 \text{ pu}
     \]

   - For the 5 MVA generators (Reactance = 12%):
     \[
     X_{5 \text{ MVA}} = \frac{12}{100} \times \frac{8}{5} = 0.192 \text{ pu}
     \]

3. **Calculate the Total Reactance:**
   - Convert to equivalent reactances for the base MVA and sum them.
   - Assume parallel operation of generators:
     \[
     X_{\text{eq}} = \left(\frac{1}{X_1} + \frac{1}{X_2} + \frac{1}{X_3} + \frac{1}{X_4}\right)^{-1}
     \]
     Where:
     \[
     X_1 = 0.144 \text{ pu (10 MVA generator)}
     \]
     \[
     X_2 = 0.144 \text{ pu (10 MVA generator)}
     \]
     \[
     X_3 = 0.192 \text{ pu (5 MVA generator)}
     \]
     \[
     X_4 = 0.192 \text{ pu (5 MVA generator)}
     \]

     \[
     X_{\text{eq}} = \left(\frac{1}{0.144} + \frac{1}{0.144} + \frac{1}{0.192} + \frac{1}{0.192}\right)^{-1}
     \]
     \[
     X_{\text{eq}} = \left(6.94 + 6.94 + 5.21 + 5.21\right)^{-1} = 0.087 \text{ pu}
     \]

4. **Add Transformer Reactance:**
   - Each transformer has 8% reactance:
     \[
     X_{\text{total}} = X_{\text{eq}} + X_{\text{transformer}} = 0.087 + 0.08 = 0.167 \text{ pu}
     \]

5. **Calculate the Fault MVA:**
   \[
   \text{Fault MVA} = \frac{\text{Base MVA}}{X_{\text{total}}}
   \]
   \[
   \text{Fault MVA} = \frac{8}{0.167} \approx 47.9 \text{ MVA}
   \]

Thus, the fault MVA on the HV side of one transformer is approximately 47.9 MVA.
0 like 0 dislike

Related questions

Two 11 KV, three-phase 2500 KVA generators having reactance of 12% operate in parallel. The generators supply power to a transmission line through a 6000 KVA transformer of ratio 11/22 KV and having leakage reactance of 4%. Calculate fault KVA on H.T. side of transformer.
Answer : To calculate the fault KVA on the high-tension (H.T.) side of the transformer, we first need to determine the equivalent reactance of the system, which includes the reactance of both generators and the ... the fault KVA on the H.T. side of the transformer is approximately **160,000 KVA**....

Show More

Two 11KV, 3-phase, 3000KVA generators having reactance of 15% operate in parallel. The generators supply power to a transmission line through a 6000KVA transformer of ratio 11/22KV and having leakage reactance of 5%. Calculate fault current and fault KVA on H.T. side of the transformer.
Answer : To calculate the fault current and fault KVA on the High Tension (H.T.) side of the transformer for the given system, we'll follow these steps: 1. **Calculate the equivalent reactance of the ... The actual fault current in amperes can be derived from the base values and the per unit fault current....

Show More

Two 11KV, 3-phase, 3000KVA generators having reactance of 15% operate in parallel. The generator supply power to a transmission line through a 6000KVA transformer of ratio 11/22KV and having leakage reactance of 5%. Calculate fault current and fault KVA on H.T. side of transformer.
Answer : To solve this problem, we will calculate the fault current and the fault KVA on the high-tension (H.T.) side of the transformer. Here's the step-by-step process: ### Given Data: - Two generators in parallel: - Voltage: ... on the H.T. side**: 1800.2 A - **Fault KVA on the H.T. side**: 68,598 kVA...

Show More

A three-phase transformer having a line voltage ratio of 0.4 kV/11kV is connected Star/Delta and protective transformers on the 0.4 kV side have a current ratio of 500/5. Calculate the ratio of ... on the 11 kV side. Draw a neat circuit diagram and indicate the given values at appropriate places.
Answer : To solve this problem, we need to find the current ratio for the protective transformers on the 11 kV side of a star-delta connected three-phase transformer. Let's break down the steps to calculate this: ### Given ... :1). - The CT ratio on the secondary (11 kV) side is approximately 20/5 (4:1)....

Show More

A 3 phase line of 4 km length delivers 4000 kW at a p.f of 0.8 lagging to a load the resistance and reactance per km of each conductor are 0.2 Ω and 0.5 Ω respectively if the voltage at the supply end is maintained at 11 kV. Calculate the received end voltage and efficiency of line.
Answer : To calculate the **received end voltage** and the **efficiency** of the transmission line, we need to follow these steps: ### 1. **Given data:** - Load power (\( P_L \)) = 4000 kW = 4000 10³ W - Power factor ... approx 10.02 \, \text{kV} \) - **Efficiency of the line**: \( \eta \approx 99.76\% \)...

Show More
Welcome to Electrical Engineering, where you can ask questions and receive answers from other members of the community.