State the procedure for laying / installation of underground cable.
1) Direct laying Cable: or Trench laying method:
Procedure:
For laying of a cable trench about 1.5m deep and 0.5m wide is made along the cable
route.
A layer of 10 cm thickness of soft soil is spread throughout the cable route in trench.
The cable is laid on this soft soil (bed)
A wall of bricks (concrete cover) is provided on either side or top of cable along the
length of cable for better mechanical protection.
Another layer of soft sand, about 10 cm thicknesses is spread throughout its cable length.
Refill the remaining trench with the help of remaining soil up to ground level.
While crossing roads (public-crossing) cable is laid through cement pipe or DWC pipe, instead of bricks for better mechanical protection.
When more than 1 cable is to be laid in the same trench, then minimum 30 cm spacing is
provided between 2 cables and gap is filled by sand.
The spacing is kept between 2 cables to reduce the effect of mutual heating and also fault
occurring on one cable does not damage the adjacent cable.
Only armored cables are used in this method.